317 NEWSTEEL
Civil Works Execution Services and Electromechanical Erection of the NS03 Plant. Location: Nova Lima / MG 08/05/2019 a 08/03/2020
MIP Engenharia is part of the history of development in Brazil. Specialized in heavy industrial assemblies, in 59 years it has become one of the main companies in the country in its area of operation. This prominent place is supported by the numbers that reveal its achievements: more than 300 industrial works completed, more than 1,000,000 tons assembled and major projects in progress.
MIP operates in the mining, metallurgy, steel, oil, energy, paper and cellulose, cement and other segments. It works side by side with companies that are a reference in their operating sectors. Its customers are some of the largest companies in Brazil and the world: Vale, Usiminas, Petrobras, Gerdau, Samarco, Acesita, Votorantim, Cenibra, Novelis and V&M do Brasil, among others.
The experience accumulated in almost six decades brings together, at MIP Engenharia, technical competence, quality in the execution of services, economic and financial solidity and respect for the safety of people and the preservation of the environment.
Civil Works Execution Services and Electromechanical Erection of the NS03 Plant. Location: Nova Lima / MG 08/05/2019 a 08/03/2020
Execution of civil and electromechanical works to implement improvements in PFF VGR II pumping in pelletizing, implantation of the vibration isolation system of the building of the primary crushing of Pumpkins II and installation of the flow meter. Execution of civil works and electromechanical erection to implement the densification of the pelletizing grinding and feeding…
Total contract for the revitalization of the port – area lv1 fire protection and fire fighting system, under a unit price regime to be executed at the Ponta da Madeira Maritime Terminal (TMPM), at Vale’s facilities, located in São Luís, Maranhão. São Luís no Maranhão. 04/22/2019 a 02/18/2020
Execution of civil and electromechanical works to replace the rotary crusher and new breaker of matacos, in the Fábrica Mine. Location: Ouro Preto / MG 04/22/2019 a 05/15/2020
Civil works and electromechanical erection for the Ore Blasting System at the Vargem Grande Mine Pelletizing Unit. Location: Itabirito / MG 10/19/2018 a 10/20/2019
Electromechanical erection fof the new tailings disposal route – Cauê Mine. Location: Itabiria – MG Period: 05/11/2018 to 02/06/2020
Civil works and electromechanical erection for the construction of ITMA and ITMD waste filtering. Location: Itabirito / MG Period: 21/05/2018 to 18/01/2020
Electromechanical erection for the Fábrica Mine Flotation System. Location: Ouro Preto / MG Period: 14/03/2018 to 23/09/2019
Optimization of the Lung Cell Discharge System and Erection of the 440TC86 belt conveyor in the Vargem Grande Mine. Electromechanical disassembly using two auxiliary crushers – Range 1 and Range 2 at the Capitão do Mato Mine. Location: Nova Lima / MG Period: sep/17 a nov/18.
Electromechanical erection of the Thickened Tailing Pumping System. Location: Oriximiná / PA Period: aug/17 a may/18.
Interconnection of the West Basin above the Boqueirão Reservoir and Adduction System at the Ponta da Madeira Maritime Terminal. Location: São Luís – MA Period: 24/02/2017 to 10/01/2019
Civil works and electromechanical erection of industrial support buildings (MRO), to be implemented at the plant, in the Ferro Carajás Project – S11D and erection of the Reactive Compensation and Harmonic Filtering System. Location: Canaã dos Carajás / PA Period: 16/11/16 to 30/09/2017